Schedule of defects
A schedule of defects (or defects schedule) is issued by the contract administrator at the end of defects liability period. It identifies defects (aspects of the works that are not in accordance with the contract) that have become apparent during the defects liability period.
The contract administrator and the contractor then agree a reasonable period within which the contractor will rectify the defects identified on the schedule. Once the contract administrator is satisfied that the defects have been rectified, they issue a certificate of making good defects which has the effect of allowing the final certificate to be issued, releasing any remaining retention.
It is important to note that the defects liability period is not a chance to correct problems apparent at practical completion, it is a period during which the contractor may be recalled to rectify defects which appear. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued. See the article on practical completion for more information.
NB: Under NEC contracts, at, or just after the defects date the supervisor issues a defects certificate, which either certifies that there are no patent defects, or lists any uncorrected defects. This is analogous to the schedule of defects. See Defects certificate for more information.
[edit] Related articles on Designing Buildings
- Certificate of making good defects.
- Contract administrator.
- De minimis.
- Defects.
- Defects certificate.
- Defects liability period.
- Handover to client.
- Latent defects.
- Liquidated damages.
- Migration strategy.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Protecting and storing rebar.
- Punch list.
- Remedial work.
- Retention.
- Schedule.
- Schedule of condition.
- Site inspection.
- Soft landings.
- Substantial completion.
Featured articles and news
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.